HGTD Overall Meeting

Asia/Shanghai
B410 (Main building)

B410

Main building

Description

Zoom link:

https://cern.zoom.us/j/63040882910?pwd=NXXbo1uBV6ltlC05dqC9US4DoUWo8C.1

  1. OTP needs to be updated
  2. Schedule
  • Sensor: 3 months delay
  • pre-production ASIC probing: ID 254 end of April 3.5
  • PEB: FDR in May
    • Jie: some of procument component are not ready
  • HV: payment of pre-prod: Shandong will pay
  • Module:
    • Polymide who pay: need to clarify
      • Joao: should not pay items not in MOU
    • Module flex: pre-prod finish in end of May, most likely to delay
    • Module assembly in July
    • Database: need double check whether the database works
      • Mei will introduce sensor database
  • DU:
    • Joao: needs to know Didier's method
    • try to finish earlier
    • manpower to CERN needed from Oct 20205 to end of 2028

3. ASIC probing update

4. Plan for moving to new clean room

  • Joao: need more details from Yunyun